Site/Civil NEW MODERN LOCK IMPROVES EFFICIENCY > Projects > New Modern Lock Improves Efficiency INSIDE THE PROJECT A new lock chamber was constructed on the Kanawha River – nine miles upstream from Charleston, West Viriginia. This new lock chamber gave much-needed additional capacity to the two existing lock chambers constructed in 1934. Å®ÓÅÒùÍÞÅàѵӪ joined efforts with Fru-Con Construction Corp., as part of a joint-venture, on this more than six-year, U.S. Army Corp. of Engineers project outside Charleston, West Virginia. Construction of the 110-foot-by-800-foot lock chamber entailed Å®ÓÅÒùÍÞÅàѵӪ moving 2.9-million cubic yards of earth and 107,000 cy of rock. In the piling portion of the project, Å®ÓÅÒùÍÞÅàѵӪ installed 216,000 linear feet of flat sheet piling and value-engineered the installation of 105,000 lf of Z-piling. In self-performing the concrete work, Å®ÓÅÒùÍÞÅàѵӪ installed and operated an on-site batch plant, which batched, hauled and placed 320,000 cubic yards of concrete. WHY IT MATTERS The addition of the new lock reduced schedule delays for barges using these, the busiest locks in the Ohio River System. The larger lock allows many more barges to be processed at once, thus increasing speed and efficiency. PROJECT DETAILS: Project Owner: U.S. Army Corps of Engineers Huntington Location: Marmet, WV Project Value: $280,000,000 SOLUTIONS: Joint Venture On-Site Batch Concrete Plant Moved 2.9 Million CY of Dirt Placed 320,000 CY of Concrete Self Performed Majority of Construction with Å®ÓÅÒùÍÞÅàѵӪ Personnel Close
INSIDE THE PROJECT A new lock chamber was constructed on the Kanawha River – nine miles upstream from Charleston, West Viriginia. This new lock chamber gave much-needed additional capacity to the two existing lock chambers constructed in 1934. Å®ÓÅÒùÍÞÅàѵӪ joined efforts with Fru-Con Construction Corp., as part of a joint-venture, on this more than six-year, U.S. Army Corp. of Engineers project outside Charleston, West Virginia. Construction of the 110-foot-by-800-foot lock chamber entailed Å®ÓÅÒùÍÞÅàѵӪ moving 2.9-million cubic yards of earth and 107,000 cy of rock. In the piling portion of the project, Å®ÓÅÒùÍÞÅàѵӪ installed 216,000 linear feet of flat sheet piling and value-engineered the installation of 105,000 lf of Z-piling. In self-performing the concrete work, Å®ÓÅÒùÍÞÅàѵӪ installed and operated an on-site batch plant, which batched, hauled and placed 320,000 cubic yards of concrete. WHY IT MATTERS The addition of the new lock reduced schedule delays for barges using these, the busiest locks in the Ohio River System. The larger lock allows many more barges to be processed at once, thus increasing speed and efficiency. PROJECT DETAILS: Project Owner: U.S. Army Corps of Engineers Huntington Location: Marmet, WV Project Value: $280,000,000 SOLUTIONS: Joint Venture On-Site Batch Concrete Plant Moved 2.9 Million CY of Dirt Placed 320,000 CY of Concrete Self Performed Majority of Construction with Å®ÓÅÒùÍÞÅàѵӪ Personnel Close